Microgrid Pre-Feasibility: How to Compare Configurations Before Procurement

Editorial production: Weimpa Inc. · Expert collaboration: Aleksander Stefanowicz
GreenTech Commercialization
Use pre-feasibility to eliminate unsuitable microgrid configurations, identify sensitive assumptions and define the evidence needed for procurement.
Microgrid pre-feasibility should narrow a decision, not create the illusion of an engineering design. Its purpose is to compare configurations on a consistent basis and show which uncertainties could change the preferred option. A polished configurator screen is useful only when its inputs, constraints and calculation boundary can be inspected.
The supplied MOVEAIR EAAS materials contain examples of configuration and cost analysis, while the introductory material describes advisory and project-development capabilities. These are supplier materials, not independently validated quotations. The following workflow uses their configuration logic without adopting their sample financial outcomes as site-specific facts.
Start with the load and service requirement
Collect a time series of demand where possible, including critical and discretionary loads. An annual electricity bill cannot reveal overnight deficits, cooling peaks or the duration of a communications outage. Record planned load growth, operating schedules and any demand that can be shifted without compromising service.
Define what must remain powered, for how long and under which contingencies. Distinguish everyday energy optimization from emergency reserve. A battery may be economical for daily cycling yet insufficient for an extended period without wind, solar or fuel delivery.
List hard constraints before sizing: available area, permissible structures, electrical interfaces, noise-sensitive boundaries, access and the ability to maintain equipment. A model should reject an infeasible configuration rather than award it an attractive cost score.
Establish a common input set
Use synchronized or appropriately reconciled wind, solar and load data. Record measurement height, data gaps, seasonal coverage and any modeled substitutions. A strong annual wind average does not tell the model whether wind coincides with the site’s deficits.
Specify losses and operating limits separately: converter efficiency, usable battery capacity, charge and discharge limits, reserve rules, generator minimum operation and curtailment. Avoid applying the same loss twice, once inside a component curve and again as a generic system allowance.
Create an input register with source, date, owner and confidence for every influential assumption. This makes later supplier discussions productive. It also prevents a provisional value from becoming an apparently confirmed design parameter as the spreadsheet passes between teams.
Compare a small set of meaningful alternatives
Begin with a credible baseline, then add changes that answer a specific question. For a remote site, this might be the existing generator and battery, additional solar and storage, and a wind-solar-storage hybrid retaining backup. Other technologies should enter only when their supply and maintenance requirements fit the site.
Alternative | Main question | Evidence needed |
|---|---|---|
Existing system improved | Can controls or maintenance reduce waste? | Baseline operating records |
Solar and storage | How much daytime surplus can serve later demand? | Irradiance, load and battery constraints |
Wind added to hybrid | Does wind reduce important deficits? | Hub-height resource and power curve |
Larger storage | Is extra reserve used often enough to justify cost? | Deficit duration and reserve policy |
Do not compare an optimized new system with a deliberately poorly operated baseline. Improvements that are available to both options should be treated consistently.
Inspect dispatch before ranking cost
Run a chronological energy balance at an interval suitable for the decision. Inspect representative difficult periods, not only annual totals. The model should explain where energy goes: direct supply, storage, losses, curtailment or unmet load.
As an illustrative screening result, configuration A might have a lower annual cost but leave 20 hours of critical demand unserved in the modeled year. Configuration B might meet the specified load at a higher cost. If the project requires that critical service, A is infeasible under the tested assumptions; it is not the cheaper equivalent service.
Then examine whether B relies on unrealistic battery charging, unlimited fuel availability or a generator that never needs maintenance. A successful numerical optimization can still represent an impossible operating arrangement.
Turn uncertainty into procurement requirements
Vary the assumptions that could change the decision: wind yield, fuel delivery cost, battery replacement, load growth and access expense. A configuration that wins only under the most favorable input combination needs stronger evidence before procurement. Where several options perform similarly, maintainability and contractual clarity may become decisive.
End pre-feasibility with a short list, a documented model and an information request. Specify the measurements, structural assessment, electrical design and binding commercial scope needed for the next decision. Keep the result labeled as pre-feasibility until those items are resolved.
For cost boundaries, see comparing CAPEX and OPEX. For storage constraints, see battery sizing for wind-solar microgrids.
Source notes: MOVEAIR - EAAS TELCO.pdf (EAAS); Intro email.pdf (Intro). PDF references: EAAS pp6-9; Intro p1. These supplied manufacturer materials describe proposals, examples and product generations; they are not independent verification of current performance. Calculations explicitly labelled illustrative are analytical examples.
Image: Illustrative microgrid configuration interface from the supplier deck; displayed numbers are sample outputs, not project quotations. Source: EAAS, PDF p7.
By Dr. Aleksander Stefanowicz. Disclosure: Aleksander Stefanowicz has a professional relationship with MOVEAIR. This is an affiliated technical analysis, not an independent product test.
Author: Dr. Aleksander Stefanowicz
Renewable energy and DeepTech advisor with an engineering background and experience in technology commercialization and strategic B2B partnerships.
Disclosure: supplied MOVEAIR materials identify him as a MOVEAIR Energy Global Partner. Supplier-related analysis reflects this professional relationship.